A49/B5477 Church Stretton Resurfacing

Published: 15th August, 2016

Notification from Highways England
Essential resurfacing works will be carried out on the A49 from the A49/B4371 crossroads to 700m north of the A49/B5477 Junction (south of Leebotwood).
Planned Start Date: 15th August 2016
Planned Completion Date: 24th September 2016
Hours of Work 20:00 to 06:00 hours (Monday to Friday).  2 way traffic lights may be in place during Saturdays as required.  Diversions via Much Wenlock will be in place.
For more information please visit www.highways.gov.uk